Which of the following best defines the term 'scope' as used in the context of project management?
答案解析
The core concept tested here is the understanding of 'scope' in project management. The correct answer is B, as 'scope' refers to the range of a project's objectives and deliverables, encompassing all the work required to complete the project successfully. Option A is incorrect because the budget is a separate aspect of project management. Option C is incorrect as the timeline refers to the project schedule, not its scope. Option D is misleading because the geographical area is not a defining feature of a project's scope.
正确答案:B